El Camino Real Rehabilitation and Improvements

Location: Arroyo Grande, CA
Client: City of Arroyo Grande

NCE completed the design and provided construction services for significant improvements to El Camino Real from Oak Park Boulevard to Grand Avenue in the City of Arroyo Grande. The project consists of pavement rehabilitation including removal and repair, pavement reinforcement fabric and pavement overlay, restriping and traffic control plans; pavement widening and striping for the addition of Class 2 bike lanes; sidewalk infill to complete a continuous pedestrian corridor; construction of a soil nail retaining wall to allow street widening; construction of various water line and utility improvements; and a redesign of the City’s Park & Ride facility to provide additional parking spaces, handicap (ADA) access, and transit amenities including a transit shelter, bike racks, and other features.

 

The “before” condition
The “before” condition
This segment received pavement grinding and overlay, widening for bike lanes, and a 300’ by 10’ high

NCE services included:

  • Topographic Survey
  • Site Layout and Planning
  • Utility design and coordination
  • Hydraulic and Hydrological Analysis
  • Class II Bike Path Design
  • Various Water Main Relocation
  • Construction Services

 
Size of Project:

1.36 miles

Construction Cost: $1,700,000

Completion Year: 2012
General Contractor:

Brough Construction, Inc.

 